0The canvas
1Estimate Evidence Card
Travels with every estimate above an agreed size. Part 1: Precision is not evidence.
| Field | Entry |
|---|---|
| Scope source and exclusions | |
| Method (comparable, bottom-up, parametric, expert, model-assisted) | |
| Comparable work and how it differs | |
| Key assumptions | |
| Dependencies and exclusions | |
| Range and confidence (low, likely, high, with drivers) | Example: 85 to 140 units, likely 105; medium confidence |
| Contingency for named risks, shown separately | |
| Reviewer (did not build the estimate) | |
| Change from last version, and why | |
| Re-baseline point |
- Every scope item has exactly one accountable work package.
- Totals by work package, role and phase reconcile.
- No reduction between versions without a scope or assumption change.
2Effort-Duration Reconciliation
Complete before a date is committed, and whenever a date is imposed. Part 2: Estimate effort before you force duration.
| Step | Output |
|---|---|
| 1. Effort, independent of date (range) | |
| 2. Real capacity (named roles, availability, start) | |
| 3. Dependencies, lead times and blocked windows | |
| 4. Derived duration range | |
| 5. Gap to the desired date, in weeks | |
| 6. Lever chosen (scope, phase, capacity, named risk, date) and owner |
3Accountability-Control Matrix
Every committed outcome mapped to the party that controls each decision and input it needs. Part 3: Fixed price, undefined scope and shared control.
| Committed outcome | Decision or input required | Who controls it | Who carries the outcome | Aligned? | Treatment |
|---|---|---|---|---|---|
| Service live by agreed date | Production environment by week 6 | Buyer platform team | Supplier | No | Dates move day for day; standby cost agreed |
Treatments for a misaligned row: move the control, move the outcome, define what happens when the controlling party does not deliver, or price the risk as named contingency.
4Requested vs Production Scope Map
Each cell: Supplier, Client, Third party, Excluded (with consequence) or Unknown. No Unknown at commitment. Part 4: The hidden half of the build.
| Requested capability | Identity and security | Data and migration | Integration hardening | Non-functional testing | Release | Operations | Support and adoption | AI evaluation |
|---|---|---|---|---|---|---|---|---|
5Solution-to-Option Canvas
Every option is the same defined solution with stated differences. Part 5: Options must come from a defined solution.
| Field | Option 1 | Option 2 | Option 3 |
|---|---|---|---|
| Outcome | |||
| Scope included | |||
| Scope excluded | |||
| Acceptance | |||
| Duration range | |||
| Delivery model | |||
| Risk holder | |||
| Key assumptions | |||
| Effort, gross-up and contingency (separate lines) | |||
| What you give up |
Keep four terms apart: cost (what delivery takes), price (what the buyer pays), value (what the buyer gains) and affordability (whether the buyer can pay, in the right budget, at the right time).
6Architecture-Funding Fit Matrix
Technical fit and funding eligibility are separate constraints. Part 6: Your best architecture may break the funding model.
| Field | Design A | Design B | Design C |
|---|---|---|---|
| Technical fit | |||
| Run-cost profile (fixed, variable, capped) | |||
| Funding line it needs | |||
| Funding line available | |||
| Period fit | |||
| Currency exposure | |||
| Run cost per accepted outcome (range, ceiling) | |||
| Gap and what would close it | |||
| Verdict |
Budget, accounting and procurement rules differ between organisations. Complete this section with your finance function.
7Delivery Boundary Schedule
One row per edge. Part 7: Price the boundary, not only the build.
| Boundary | What crosses it | Owner before | Owner after | Service level | Commercial treatment | Ends or reviewed |
|---|---|---|---|---|---|---|
| Go-live to hypercare | ||||||
| Hypercare to warranty | ||||||
| Warranty to support | ||||||
| Production release | ||||||
| Cloud subscription and consumption | ||||||
| AI model change | ||||||
| Third-party services | ||||||
| Exit |
- A defect is defined separately from a change and from an incident.
- Hypercare and warranty have end dates.
- The cloud and AI bill has an owner, a ceiling and an alert.
8Re-Baseline Trigger Card
Agreed by both parties at signature. Reaching a trigger creates an obligation to re-plan. Part 8: Re-baseline before the variance becomes a surprise.
| Trigger | Agreed threshold | Checked at | Who raises it | Required response |
|---|---|---|---|---|
| Key assumption fails | ||||
| Effort variance on a work package | Example: more than 15% above plan for work completed | |||
| Scope inventory growth | ||||
| Dependency delay | ||||
| Contingency drawn faster than progress | ||||
| Accepted outcomes behind plan | ||||
| AI cost per accepted outcome above range | ||||
| Key role vacant |
At every checkpoint compare four things against the last baseline: assumptions, scope, effort for work completed, and evidence of accepted outcomes. Then decide: continue, re-baseline (unknown or shared cause), change request (buyer-driven) or recovery plan (supplier-driven).