By the third week of discovery at the illustrative wholesale distributor in this series, the requirement list had reached ninety lines. It looked complete. It had sections, priorities and a column of ticks. Line 41 read: "The solution must integrate with the order system." Line 63 read: "Orders must be confirmed to the customer within fifteen minutes." Line 78 read: "Customer data must be accurate."
Each line was reasonable. None of them could be built as written. Line 41 hid at least three choices: whether orders would be written in real time or in batches, which system would own the customer reference, and who would maintain the mapping between them. Line 63 hid a choice about what "confirmed" meant when an order was waiting in the exception queue from part 3. Line 78 had no owner and no test.
The list was a record of what people wanted. It was not yet a basis for commitment, because the decisions inside it had not been made, and nobody had been asked to make them.
A requirement inventory becomes decision-ready only when each line has an owner, a confidence level, an acceptance test and the unresolved choices behind it made visible, with a person and a date for deciding each one.
Five kinds of statement in one list
Requirement lists mix statements that need different handling. Separating them is the first step.
| Kind | What it is | Example (illustrative) | How to handle it |
|---|---|---|---|
| Requirement | A need the solution must meet, testable | Orders are acknowledged to the customer within fifteen minutes during trading hours | Give it an owner and an acceptance test |
| Constraint | A limit the solution must respect | Customer personal information stays in systems covered by existing agreements | Record its source; confirm whether it is hard or soft |
| Assumption | Something believed true but not confirmed | The order system's email intake can be used at current volumes | Move to the Hypothesis Register from part 2 and test it |
| Preference | A wish that is not essential | "Use the same platform as the marketing team" | Label it. Trade it if it costs too much |
| Decision | A choice that has been made, or must be | Orders are written to the order system in real time | Record it with its owner, status and consequences |
CloudNala's earlier requirements, assumptions and traceability explains how to separate facts, assumptions and commitments when responding to a tender, and how a traceability matrix catches gaps. From discovery evidence to architecture decision sets out an extended decision record that cites its evidence. This part sits between the two: it shows how to find the decisions hidden inside requirements before they become either a bid response or a decision record.
Every requirement hides a choice
A requirement written without its choices looks settled and is not. Three patterns are common.
- Integration requirements ("must integrate with X") hide direction, timing, ownership of data and responsibility for failure.
- Quality requirements ("must be accurate", "must be fast") hide a measure, a threshold and who decides when the threshold is met.
- Scope requirements ("must support all channels") hide which channels come first and what happens to the others meanwhile.
If these choices are not made in discovery, they are made later by whoever is building the solution, usually under time pressure and without the authority to make them. The sponsor discovers them when the delivered solution behaves in a way nobody expected.
The Decision-Ready Requirement Card
The decision tool for this part is a card for each requirement that matters to the decision. Not every line needs one. Cards are worth writing for requirements that drive cost, risk, architecture or acceptance.
| Field | Question | Example for line 41 (illustrative) |
|---|---|---|
| Requirement | What is needed, in testable words? | Orders captured from email and WhatsApp reach the order system without re-keying |
| Need behind it | Which outcome does it serve? | Reduce order desk effort and missed cut-offs |
| Source and date | Who stated it, when, in what document? | Sales director, discovery workshop, week one |
| Owner | Who can accept it, change it or trade it away? | Operations manager |
| Confidence | Stated, observed or validated? | Observed (re-keying measured), not yet validated against volumes |
| Acceptance | How will we know it is met? | A month of orders with no re-keying, and the exception rate below an agreed level |
| Unresolved choices | What must be decided before it can be built? | Real-time or batch writing; which system owns the customer reference; who maintains the mapping |
| Decision owner and decide-by | Who makes each choice, and by when? | Operations manager and finance manager, before the build is scoped |
| If not decided | What happens by default, and what does that cost? | The builder chooses batch for simplicity; confirmations miss the fifteen-minute target |
The last field is the one sponsors tend to read. It turns an abstract open question into a concrete consequence, which is usually what it takes to get a decision on the agenda.
Confidence is not priority
Many lists rank requirements by priority (must, should, could) and stop there. Priority tells you how much a requirement matters. It does not tell you how sure anyone is that the requirement is right.
A "must" with low confidence is a risk. It is likely to change, and anything built around it may need to be rebuilt. The card records confidence separately, in three levels:
- Stated: someone said it.
- Observed: the discovery team saw evidence of the need.
- Validated: the need was tested, and its acceptance criterion agreed with its owner.
High-priority requirements at "stated" confidence are where discovery should spend its remaining time.
From open choice to decision record
Each unresolved choice on a card is, in effect, a decision record waiting to be written. Michael Nygard's widely used format for architecture decision records (2011) includes a status: a decision is "proposed" until stakeholders agree and "accepted" once they do, and a later decision can mark an earlier one "superseded". The card's open choices map neatly onto that lifecycle. When discovery ends, each one should be either accepted, with its record written, or listed in the decision pack as an open decision with an owner and a date.
At the distributor, the ninety-line list produced eleven cards and fourteen open choices. Nine were decided before discovery closed. Five went into the final decision pack, described in part 7, as decisions the sponsor had to make before any build could be scoped.
What this means for South Africa
South African tender specifications often arrive as long requirement lists, and suppliers are expected to respond line by line. The choices hidden in those lines do not disappear because the procurement format does not ask about them. A supplier can respond in the required structure and still state, as assumptions or clarification questions, the choices it believes the buyer must make. Buyers, in turn, can reduce disputes later by writing decision-ready requirements in the specification itself. Procurement rules vary by sector and organisation, so this is general information, not procurement advice.
A requirement review checklist
- Is each line labelled as a requirement, constraint, assumption, preference or decision?
- Does each requirement that drives cost, risk or architecture have a card?
- Does every card have an owner who can trade it away?
- Is confidence recorded separately from priority?
- Does every unresolved choice have a decision owner and a decide-by date?
Next in the series: Discovery must end with a choice. Previous: Part 5, Ask what should be left alone. All parts are on the series page.
Sources and limits: the architecture decision record statuses are paraphrased from Michael Nygard's "Documenting Architecture Decisions" (Cognitect blog, 15 November 2011, checked on 24 November 2026). The five kinds of statement and the Decision-Ready Requirement Card are CloudNala analysis. The distributor, its requirement list and its counts are an illustrative composite. Procurement statements are general information, not advice.
How CloudNala can help
CloudNala turns requirement lists into decision-ready inventories. We separate requirements from constraints, assumptions, preferences and decisions, write cards for the lines that drive cost and risk, record confidence beside priority, surface the choices hidden in each line and put every open choice in front of a named decision-maker with a date, before anyone is asked to build or price it.
Work with CloudNala
CloudNala helps organisations move from technology ambition to practical execution across cloud, AI, data, platform engineering and digital services.
Whether you are exploring AI, modernising your cloud environment, building a public-sector digital service, or turning an idea into a working MVP, we can help you shape the roadmap and deliver the next step.
Book a CloudNala Discovery and Decision Pack or write to us at consult@cloudnala.co.za